Senior Project
Scheduler
Lake Charles, LA
From: February 2016
to August 2016
Performance
Inc.
Sasol Project
* Create and
Maintain P6 Schedule for the Cracker area of the Project
* Chair daily and
weekly meetings to report on progress and create workarounds for arising
issues
* Evaluate budget
and report PF based on Earned hours versus burned
* Create 3 wk look
ahead reports for review by upper management and client
* Create Weekly reports
for distribution that include write up on work completed this wk, work
planned next week and work planned for next 3 weeks. Also included Mn Hrs
burned to date, and this week versus Earned to date and for the week.
S-Curve charts by discipline with hours planned, earned and burned and
manpower for the same.
* Created delay
logs to show where lost time was potentially generated. Rain, lighting,
crane down, etc.
* Analyze schedule
impacts relating to project schedule trends/risks to develop mitigation strategies.
* Interface with
field supervision in order to mitigate issues that effected field work and
progress.
Lead Senior Project
Scheduler
Midway, TN
From: June 2015 to
February
2016
Performance
Inc.
US Nitrogen plant
Led a team of
Scheduler/Planners
* Oversee reporting matrix of all documents including manpower, man
hours, spent, earned, productivity and all scheduling related issues.
* Evaluate and
validate budget and resource assignments
* Analyze impacts
related to baseline schedule and current trends in order to identify risks
and develop a workaround plan to keep project on schedule.
* Chair daily and
weekly progress meetings to highlight potential problem areas and created
mitigation strategies for all contractors to come together working to a
common goal.
*Create mn hrs/mn
pwr charts, S curve and progress reports for management and client review.
Project Controls Specialist /
Manager
Geismar, LA
From: August 2013
to February 2016 Alberty &
Associates
Huntsman/Rubicon plant
G500 MDI and HCL
Handling Expansion / De-Bottle neck project
*Oversee project
scheduler training in accordance with facility requirements
*Perform
evaluations of contract budget and baseline resource assignments
*Provided
assistance to external and internal teams as needed to ensure adherence to
timelines
*Coordinate with
engineering and field supervision in order to facilitate proper progress
and manpower forecast
*Create and Provide
Manpower S Curve charts and progress reports to upper management
*Chair weekly
coordination meetings with contractors in order to provide accurate path
forward for remaining work
*Analyze schedule
impacts relating to project schedule trends or risks in order to develop
mitigation strategies.
Sr. Specialist / Planning
Scheduling
From: June 2013 to
August 2013
Kellogg Brown &
Root
Victoria Texas
Responsible for
training and setting up a successful Project Controls Team that could….
*Prepare and
maintain Proper Document Control Documents
*Build, maintain
and execute Project and Turnaround Schedules using P6 version 7
*Analyze impacts on
the schedule and create mitigation strategies
*Overall merge the
Document Control, Planning and Scheduling departments to create an
environment of success from integrated efforts.
Project Controls Specialist
From: April 2012 to
May 2013 Fluor/Amec Joint
Venture Mt. Milligan, BC
Copper/Gold Mine
$900-million Open
pit Copper-Gold Mine Engineering & Construction
*Maintain large
Engineering, Procurement & Construction Master Schedule in Primavera P6
Version 8.3
*Integrate
engineering and construction schedules into the Master Schedule as required
for 15 contracts
*Create and
Integrate schedules for numerous smaller subcontractors
*Analyze schedule
impacts relating to project schedule trends or risks to develop mitigation
strategies.
*Interface with
management and clients on all engineering and construction schedule related
issues
*Interface with field
supervision to perform long-term and short-term engineering field
scheduling
*Bimonthly progress
updating in Primavera P6
*Generate Primavera
P6 & Excel based engineering & construction management reports
*Narrative input to
weekly and monthly engineering reports
Lead Project Scheduler
From: Aug 2009 to
April 2012 Kellogg Brown &
Root Delisle, Ms., Titanium
Dioxide Plant
$4.5 Million Quad
Clone Replacement
$8.6 Million New
Generation Ore Recovery EPC project
$14.4 Million Environmental
Support Facilities Expansion
$55 Million
Titanium Incremental Capacity Upgrades
*Create and
Maintain Comprehensive Resource loaded Schedules with Primavera P6 Version
7 for Long Term Projects, as well as shutdowns and multi day outages.
*Work directly with
field superintendents and sub contractors to create logical relationships
and time lines in order to facilitate proper schedule projections.
*Reporting directly
to upper management, baseline and path forward for manpower needs and
resource allocation.
*Analyze schedule impacts relating to project schedule trends or
risks and develop mitigation strategies.
*Create 4wk look
ahead, and percentage reports for presentations at weekly meetings.
*Create and maintain Master Schedule for all workload including
Major projects, work orders and upcoming shutdowns.
Planner/Scheduler
From: Jan 2007 to
Aug
2009
Zachry
Delisle, Ms., Titanium Dioxide Plant
*Creating footage
reports, and keeping up with isometric books for all projects
*Reading and
Redlining Equipment Arrangement drawings
*Work directly with
field superintendents and sub contractors to create logical relationships
and time lines in order to
facilitate proper schedule projections with Primavera P6 Version 7.
*Keeping up with
material received, and with material sent to the field
*Running PDMS CAD review program and troubleshooting
field installation problems.
Planner/Scheduler
From: April 2006 to Dec
2006
Zachry
Delisle, Ms., Titanium Dioxide Plant
*Use of Primavera P6 Version 7 to facilitate
Schedule projections
*Reporting to upper management, baseline and path
forward for manpower and resource allocation
*Analyze schedule impacts relating to project
schedule trends or risks and develop mitigation strategies
|